Docket No. | Op. Below | Argument | Opinion | Vote | Author | Term |
---|---|---|---|---|---|---|
13-787 | Mo. | N/A | N/A | N/A | N/A | OT 2013 |
Issue: Whether the filed rate doctrine and Supremacy Clause permit a state public service commission to “trap” federally approved costs with a utility by recognizing the prudency of obtaining electric power from a plant in another state, but then barring the utility from recovering the Federal Energy Regulatory Commission-approved transmission costs of importing that power. CVSG: 03/10/2014.