Docket No. | Op. Below | Argument | Opinion | Vote | Author | Term |
---|---|---|---|---|---|---|
13-445 | 7th Cir. | N/A | N/A | N/A | N/A | OT 2013 |
Issue: (1) Whether the cost-causation principle underlying the “just and reasonable” standard of the Federal Power Act permits the socialization of costs across a regional transmission network without regard to the actual costs caused or benefits received by customers required to pay those costs; and (2) whether an administrative agency may concededly rely upon extra-record evidence without providing the parties notice and an opportunity to rebut that evidence.
Date | Proceedings and Orders |
---|---|
Aug 16 2013 | Application (13A191) to extend the time to file a petition for a writ of certiorari from September 5, 2013 to October 7, 2013, submitted to Justice Kagan. |
Aug 19 2013 | Application (13A191) granted by Justice Kagan extending the time to file until October 7, 2013. |
Oct 7 2013 | Petition for a writ of certiorari filed. (Response due November 8, 2013) |
Oct 7 2013 | Appendix of Hoosier Energy Rural Electric Cooperative, et al. filed. |
Oct 24 2013 | Waiver of right of respondent Public Service Commission of Wisconsin to respond filed. |
Oct 28 2013 | Waiver of right of respondent PJM Interconnection, L.L.C. to respond filed. |
Oct 29 2013 | Waiver of right of respondent Illinois Commerce Commission to respond filed. |
Oct 30 2013 | Order extending time to file response to petition to and including December 9, 2013, for all respondents. |
Nov 1 2013 | Waiver of right of respondent Michigan Public Service Commission to respond filed. |
Nov 21 2013 | Waiver of right of respondent Organization of MISO States, Inc. to respond filed. |
Nov 22 2013 | Order further extending time to file response to petition to and including January 8, 2014. |
Jan 3 2014 | Waiver of right of respondents Madison Gas and Electric Company, et al. to respond filed. |
Jan 8 2014 | Brief of respondent Federal Energy Regulatory Commission in opposition filed. VIDED. |
Jan 8 2014 | Brief of respondents Midcontinent Independent System Operator, Inc., and Midwest ISO Transmission Owners in opposition filed. VIDED. |
Jan 21 2014 | Reply of petitioners Hoosier Energy Rural Electric Cooperative, et al. filed. |
Jan 22 2014 | DISTRIBUTED for Conference of February 21, 2014. |
Feb 7 2014 | Letter of respondent Federal Energy Regulatory Commission received. VIDED. (Distributed) |
Feb 24 2014 | Petition DENIED. |